In order to improve the transfer capability of the 220-500 kV AC transmission system that forms the power network backbone in the Russian Far East Interconnected Power System, two new generation System Protection Schemes complexes were put into operation at the Zeya and Bureya Hydro Power Plants. Putting into operation was accompanied by the series of full-scale tests. The peculiarities of the fullscale experiments were participation of the experts trom Russia, Switzerland, Italy and the USA, and implementation of diverse Phasor Measurement Units devices and Digital Fault Recorders produced in different countries such as the USA, Sweden, Belgium and Russia.
Full-scale Tests of the AC Transmission System to Examine the New SPS Complexes / Grobovoy, ; Bondareva, N.; Borodina, N.; Denisova, D.; Germond, A.; Cherkaoui, R.; LA SCALA, Massimo; Bruno, Sergio; Benedictis, M. DE. - (2006), pp. 4-8. (Intervento presentato al convegno 8th IEE Int. Conf. AC and DC Power Transmission tenutosi a London nel 28 – 31 March 2006,).
Full-scale Tests of the AC Transmission System to Examine the New SPS Complexes
LA SCALA, Massimo;BRUNO, Sergio;
2006-01-01
Abstract
In order to improve the transfer capability of the 220-500 kV AC transmission system that forms the power network backbone in the Russian Far East Interconnected Power System, two new generation System Protection Schemes complexes were put into operation at the Zeya and Bureya Hydro Power Plants. Putting into operation was accompanied by the series of full-scale tests. The peculiarities of the fullscale experiments were participation of the experts trom Russia, Switzerland, Italy and the USA, and implementation of diverse Phasor Measurement Units devices and Digital Fault Recorders produced in different countries such as the USA, Sweden, Belgium and Russia.I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.